Nile Basin’s potential for hydroelectric power is quite substantial. The Blue Nile drops some 1,360-m between Lake Tana and its exit point into Sudan. Coupled with its substantial discharge, the Blue Nile has the largest hydropower potential in the Nile Basin. A number of sites with high hydropower potential have been studied in the past.






Projected increment in installed capacity
Looking into the future, existing national plans indicate a substantial increase in installed capacity in the period 2017 – 2050. Projected growth in aggregate installed capacity in the Nile Basin is shown in the adjacent chart. The total increase in installed capacity by about 2050 will be over 20,000 MW bringing the total installed capacity to about 26,000 MW. Most of the increase is expected to be in the Blue Nile sub-basin. The GERD will inject 6000 MW of installed capacity. The Rusumo falls project, which is the first hydro-electric power project cooperatively implemented by Burundi, Rwanda and Tanzania with the facilitation of NBI will produce 81 MW.

Power Plants in the Basin
Uganda’s Bujagali Hydroelectric Power Plant Financing through Public-Private Partnerships’
Despite being one of Africa’s fastest growing economies, Uganda had one of the lowest electrification rates in the world. Only 2% of its rural population had access to electricity, and the country suffered from frequent rolling blackouts – requiring expensive emergency generation, costing USD 9 million per month. In 2007, to meet these shortfalls, the government decided the least cost option – a USD 860 million hydroelectric power plant in Bujagali, 8 km down the Nile from Lake Victoria. However, it needed financiers and large hydropower developers to implement the project. The government established a public-private partnership called Bujagali Energy Limited, which would own the plant for a 30-year concessionary period before transferring it to Uganda.
The project which was regionally identified through the NELSAP SSEA, will enhance power trade with neighboring Kenya, through the Nile Basin Initiative Planned Kenya-Uganda Interconnector Multilateral lenders including the World Bank, the European Investment Bank, and the African Development Bank joined in with private financiers, such as South Africa’s ABSA Capital and Standard Chartered Bank. Commissioning of the dam took place in August 2012. Today the 250 MW hydropower plant meets half of Uganda’s energy needs. The project’s construction created over 3,000 local jobs. Bujagali was registered in 2012 as a Clean Development Mechanism project, making it the largest ever registered in a Least Developed Country.
Power Plants in the Basin- The Tekeze Hydroelectric Power Plant
The dam is located on the Tekeze River, a tributary of the Nile, in a mountainous region of Ethiopia. At 188m high, the Tekeze Arch Dam ranks as the highest dam in Africa, eclipsing the previous record height for an African dam of 185m held by the Katse Arch Dam in Lesotho. It generates 300 MW adding 40% energy to the 683 MW previously generated for the entire country. The dam impounds a 70-km-long reservoir. An underground powerhouse, containing four 75 MW Francis Turbines, is located 500 mm downstream from the dam and fed by a 75-m-high intake structure connected by a 500-meter-long concrete-lined power tunnel. A 105-km-long 230 kV double-circuit transmission line was constructed through rugged, mountainous terrain with minimal environmental impact to connect to the Ethiopian national grid.